Excavation Calculator

Calculates the excavation volume from length, width, and depth — the same rectangular-prism formula applies to a single pit, a trench (using trench run and width), or a set of footing pits (using quantity).

Formula

Volume per cut = Length × Width × Depth. Total volume = Volume per cut × Quantity.

Assumptions

Assumes a simple rectangular (or rectangular-trench) cut with vertical sides — it does not account for sloped/battered sides, which some soil types or safety regulations require.

Results are estimates for general guidance and do not replace verified calculations from a qualified professional where accuracy is critical.

How it works

Select what you're excavating (a label only — it doesn't change the math), then enter length, width, depth, and quantity.

How excavation volume is calculated

An excavation calculator works out how much soil you'll remove from a hole with straight, vertical sides: length × width × depth. Multiply by the number of identical holes for a set of footing pits. The result, in cubic meters and cubic feet, is the in-ground (bank) volume used to price digging, plan spoil removal and size backfill.

The formula

  • Volume per cut = Length × Width × Depth
  • Total volume = Volume per cut × Quantity

The same rectangular-prism formula covers all three excavation types in the selector:

Type Length Width Quantity
Open pit Pit length Pit width Usually 1
Trench Total trench run Trench width Usually 1, or one per separate run of equal size
Footing Pad length Pad width Number of identical pads

Each dimension can be in mm, cm, m, ft or in. Results are rounded to three decimal places.

Worked examples

Strip footing trench: a trench 10 m long, 0.6 m wide and 1.2 m deep.

  1. Volume per cut: 10 × 0.6 × 1.2 = 7.200 m³.
  2. Quantity is 1, so the total is 7.200 m³, or 254.266 ft³.

Column footings: six pads, each 1.5 m × 1.5 m and 1.2 m deep.

  1. Volume per pad: 1.5 × 1.5 × 1.2 = 2.700 m³.
  2. Total: 2.7 × 6 = 16.200 m³, or 572.098 ft³.

Trenches with sloped sides

Deeper excavations often can't have vertical walls, because the sides have to be cut back to a safe angle. The calculator doesn't model slopes, but you can still use it. For a trench sloped equally on both sides, the cross-section is a trapezoid, and its area equals depth × average width:

Average width = Bottom width + (Slope ratio × Depth)

where the slope ratio is horizontal distance per unit of depth. In the US, OSHA's Appendix B to Subpart P sets maximum allowable slopes for excavations less than 20 ft deep:

Soil or rock type Maximum slope (H:V) Angle from horizontal
Stable rock Vertical 90°
Type A ¾ : 1 53°
Type B 1 : 1 45°
Type C 1½ : 1 34°

Example: the 10 m trench above, 0.6 m wide at the bottom and 1.2 m deep, cut back at 1:1 on both sides. The top width is 0.6 + 2 × 1.2 = 3.0 m, and the average width is 0.6 + 1 × 1.2 = 1.8 m. Entering 10 × 1.8 × 1.2 gives 21.600 m³, three times the vertical-sided volume. That difference is why the slope matters when you price a job.

Steps to estimate an excavation

  1. Pick the excavation type so you remember what each dimension means.
  2. Measure the bottom dimensions of the cut, including any working space you need around a footing or pipe.
  3. Measure depth from the existing ground level, not from a finished level. On sloping ground, average several depth readings.
  4. If the sides will be sloped, replace the width with the average width as shown above.
  5. Enter the quantity of identical cuts and read off the volume.

What the result doesn't include

  • Bulking. Dug soil loosens and occupies more volume than it did in the ground, and compacted fill occupies less. The figure here is the undisturbed volume.
  • Benching, stepped sides or shoring. Trench boxes and shoring change the width you dig, so measure to the outside of the support system.
  • Irregular shapes. Split them into rectangles and add the volumes.

Safety

This is a quantity estimate only. OSHA's trenching fact sheet says trenches 5 feet (1.5 m) or deeper need a protective system unless they're entirely in stable rock, and those 20 feet (6.1 m) or deeper need one designed or approved by a registered professional engineer. Follow your local regulations and have a competent person or engineer decide the support method for your site.

Related calculators

Last updated

Frequently asked questions

How do I calculate excavation volume?
Multiply length × width × depth for one cut, then multiply by the number of identical cuts. A trench 10 m long, 0.6 m wide and 1.2 m deep is 10 × 0.6 × 1.2 = 7.2 m³.
Does the excavation type change the formula?
No. Pit, trench and footing excavations all use the same length × width × depth formula. The type is a label to help you remember what the dimensions refer to.
Does this account for sloped trench walls?
No, it assumes vertical sides. For a trench with sloped sides on both faces, enter the average width instead, which is the bottom width plus the slope ratio × depth. A 0.6 m wide, 1.2 m deep trench sloped at 1:1 has an average width of 1.8 m.
Will the soil I dig out fit in a truck of the same volume?
Usually not. Soil loosens and takes up more space once it's dug out, so the volume you haul is larger than the in-ground volume this calculator gives. Ask your haulage contractor what allowance they use for your soil type.
How do I convert the result to cubic yards?
Divide the cubic feet figure by 27, or the cubic meters figure by 0.7646. A 7.2 m³ trench is 254.266 ft³, about 9.42 cubic yards.